Overview
On an AGT BLOK 400, a fixed bulk wire drum makes sense only if the wire feeds reliably at every rail position and arm posture the job calls for.
- If a carriage-mounted drum avoids a long conduit run or tight bends, ask the integrator to quote it. Check the conduit’s rated minimum bend radius through transverse travel and arm motion, too.
- Decide where the welding power source belongs separately. Ask for a layout drawing that shows where the drum, feeder, power source and facility connections go, and distinguishes the wire route from power, shielding-gas and control lines that cross to the carriage.
- Have the integrator run a guarded, arc-on trial with the specified wire type, diameter and package and the proposed feeder, conduit and torch. Use the shop’s applicable welding procedure and inspection criteria.
- Compare starts and sustained welds on joints with similar geometry and fit-up near both ends of the required travel. Test the most demanding routing posture wherever it occurs. The weld trial doesn’t replace the cell’s safeguarding review.
On an AGT BLOK 400, keep the bulk wire drum stationary only if the proposed route feeds reliably at every rail position and arm posture the job requires. If mounting the drum on the carriage avoids a long conduit run or tight bends, ask the integrator to quote that layout. Prove the selected route with comparable welds near both ends of the working travel, and decide separately where the welding power source belongs.
What THG’s two rails move
Indianapolis-based THG Automation showed MobileRunner at FABTECH on October 21–23, 2026. Its November 12, 2026 product release detailed CobotRunner, which THG had already previewed in its show plans. The table- or floor-mounted CobotRunner moves the cobot and its mounted accessories. MobileRunner moves the complete THG Mobile Platform and its mounted process equipment. Even with an integrated cable chain, MobileRunner’s rail extensions are limited by cable reach.
For Indiana fabricators pricing a separate AGT cell, the distinction is what travels with the robot. Moving the torch farther doesn’t tell you whether the electrode wire can feed there or which connections still have to flex.
Fixed vs. traveling wire drums
The BLOK 400 cantilevered gantry moves the welding robot lengthwise along the floor rail and across the work on its transverse beam. That makes it a candidate for welding accessible fillets at both ends of a fixtured steel skid or repeated crossmember joints on an equipment or trailer frame without turning the assembly. If the part or fixture blocks a joint, a longer rail won’t expose it. Workpiece positioning is a separate choice.
The gantry has mounts for the welding power source and the bulk wire drum, which AGT calls a bulk wire barrel. With a fixed drum and a moving feeder, the conduit may need to span a long run at the far end of the rail, but its tightest bend can occur elsewhere. Bending the conduit below its rated minimum radius can make the wire feed unevenly. If the drum and feeder both ride with the carriage, lengthwise travel need not increase their separation. Transverse travel and arm motion can still change the wire path, so check the proposed routing against the limits of the actual feed equipment.
For an AGT BLOK robotic welding system quote, ask for a drawing that locates the drum, feeder, power source and facility connection points. It should distinguish the electrode wire route from any power, shielding-gas or control lines that cross from fixed equipment to the carriage. A mounting provision gives the integrator a layout to evaluate; the quote should say which equipment is included.
Prove the wire route with representative welds
Have the integrator run a guarded, arc-on trial with the specified wire type, diameter and package and the proposed feeder, conduit and torch. Compare starts and sustained welds on joints with similar geometry and fit-up near both ends of the required travel. Test the most demanding routing posture too, even if the tightest bend occurs mid-rail. Use the shop’s applicable welding procedure and inspection criteria. A dry run can check reach and clearance, but it cannot show how the setup welds. The weld trial does not replace the cell’s safeguarding review.
I’m Adam Quoss, Vice President of Sales at Mac-Tech. Bring a frame or skid drawing with the fixture, torch approaches and representative welds near both ends marked, along with the wire you plan to run. I can help you assess what should travel with the robot, what belongs in the AGT BLOK quote and what to ask the integrator to demonstrate before you commit.
Sources
- THG Automation Introduces CobotRunner Linear Rail System
- FABTECH REPORT: THG Automation extends cobot reach with MobileRunner
- THG Automation MobileRunner Linear Track
- MobileRunner Robotic Linear Rail for THG Mobile Platform
- BLOK-HEAVY: Robotic Welding for Medium to Large Parts
- AGT BLOK Robotic Welding Systems
- MasterLiner Maxi Flex/HD; Basic Flex/HD Operating Instructions
- OSHA Technical Manual, Section IV, Chapter 4: Industrial Robot Systems and Industrial Robot System Safety