Robotic Welding Restart After Arc Loss

Overview

Put mid-seam loss of an established arc in your AGT BLOK quote as a commissioning test. Ask the supplier to show whether the cell can finish the seam to the job’s welding requirements and how the shop prevents release if the weld is unfinished or can’t be verified.

  • Start with an accessible skid fillet. Mark where deposition ended, where the torch stopped, and, if it restarts, where deposition resumes relative to the existing bead. Have your welding-quality lead set inspection and acceptance criteria beforehand. Compare with an uninterrupted weld on the same joint design using the same procedure.
  • Retest where access changes the torch approach or programmed path. On multipass work, have the operator identify the interrupted pass and show how it’s held for review before another pass covers it.
  • Check what the operator interface reports and how the operator identifies the affected joint or pass and keeps the assembly on hold. Don’t assume the alarm identifies the weld.
  • Have a qualified integrator run the demonstration under an approved test plan with safeguards in place. Keep it separate from protective-stop testing and safeguard validation.

Before buying an AGT BLOK cell for recurring steel frames or skids, have the integrator demonstrate what the quoted cell does when an established arc goes out mid-seam. The test should show where the bead ended, whether the cell can finish the seam to the job’s welding requirements, and how the shop keeps an unfinished or uncertain weld from being released. Resumed motion or a cycle-complete message does not prove the weld is finished or acceptable.

Find where deposition stopped and restarted

A straight, accessible rail-to-crossmember fillet on a recurring steel skid is a useful first test: it gives the team a clear place to locate the end of the bead and inspect the restart. Run an uninterrupted comparison weld on the same joint design using the same welding procedure. On the interrupted weld, have the integrator distinguish where deposition ended from where the torch came to rest. If the cell can restart, have the integrator show where it deposits weld metal again relative to the existing bead.

FANUC ArcTool illustrates why those locations can differ. With arc-loss monitoring enabled, the documented function raises an alarm when the arc-detection signal stays off for the configured interval. If the torch keeps moving during that interval, it can stop beyond the bead end. The reviewed ArcTool manual limits its overlap function to linear welding motion at a hold; it does not apply that function to circular or circular-arc motion. That is not proof of overlap after an arc-loss alarm on the quoted cell. A failed initial strike, a planned hold, and a protective stop are not substitutes for losing an established arc after deposition has begun.

Arc starts and stops are quality-sensitive in gas metal arc welding. Have the shop’s welding-quality lead specify how to inspect the restart area and what qualifies as acceptable before the demonstration. The uninterrupted weld gives the team a comparison, but even a continuous-looking restart has to meet the job’s criteria.

Retest where access or the weld pass changes

AGT BLOK Robotic Welding Systems are modular. In the BLOK-HEAVY family, a rail-mounted cantilevered gantry brings the welding robot to joints distributed across large frames and skids. The BLOK 500 adds vertical positioning for deeper access. Customer-supplied tables or trestles can support a stationary assembly, while an optional positioner can change its orientation. These choices help present the joint to the torch; they do not prove that the torch can retrace and restart on every path.

Use a recurring frame joint beside a stiffener as a second test if the obstruction changes the torch approach or the programmed path. For multipass work, have the operator identify the interrupted pass and show how the weld is held for review before another pass covers it. A successful restart on the open skid fillet does not settle either case.

Specify when the cell restarts and when the weld stays on hold

Have the quote identify the controller and software revision, welding power source, and operator interface, then state which paths and arc-loss conditions the supplier will demonstrate at commissioning. If the cell cannot finish the seam or the result cannot be verified, have the operator show what the interface reports, how they identify the affected joint or pass, and what prevents release of the assembly. An alarm can flag the event without identifying the weld, so don’t assume automatic joint tracking. If a recurring seam can only be held for review, plan for that work rather than counting it as automatic recovery.

Have the qualified integrator conduct the demonstration under an approved test plan with safeguards in place. Keep the process-recovery test separate from protective-stop testing and safeguard validation.

I’m Adam Quoss, Vice President of Sales at Mac-Tech for Illinois and Indiana. If you’re evaluating a BLOK cell for frame or skid work in Indiana, bring an assembly drawing with the joint you’d least want to leave unfinished marked, along with the proposed workholding, any pass sequence, and the job’s welding and inspection requirements. I can help you and the supplier put the right joint, restart behavior, and operator response into the quote and commissioning demonstration.